Problem faced by Client
Our client, an energy company, was named in a large
complex toxic tort case. The plaintiffs in the case alleged that our
client abandoned electric transformers with PCB’s near public housing.
Greene and Letts was retained within a year of trial. This case was
challenging because it involved:
-
approximately 7000 plaintiffs. -
complex causation issues. -
severely limited time to prepare matter for trial due to the late stage
that Greene and Letts was brought into the case
Outcome Desired by Client
The client wanted to reduce the 7000 plaintiffs to a
manageable number to pave the way for a favorable settlement or effective
defense at trial.
Defense Strategy employed by Greene and Letts:
Aggressive Discovery and Motion Practice
Greene and Letts conducted
a large number of depositions in a short period of time followed by
aggressive motion practice. This laid the framework for dismissal of more
than 94% of the plaintiffs.
Outcome Obtained by Greene and Letts
The overall number of plaintiffs was reduced by 94%
from 7000 to 400. This set the stage for a favorable settlement that
required our client to pay less than $2,500 per plaintiff.
Client Reaction
The client was very impressed with the way the case
was handled and viewed the settlement of the case with less that 6% of the
original plaintiffs as a victory. |